Employer: The ministry of Energy- Khouzestan Water and Power Authority
Project Geographical position: Kouzestan Province, Ramshir county
Project Description:
The Ramshir irrigation and drainage network is the fourth network of Maroon reservoir dam downstream five networks which is located after Behbahan, Jayzan and Ramhormoz irrigation and drainage networks. This plan was implemented in order to proper distribution of the part of water reservoir of Maroon dam and increasing the farm land and agriculture development through of irrigation and drainage network construction with a breadth of 10000 hectare of these areas approximatly.
The major executing activities supervision which this consulter was responsible for are as follows:
The irrigation pond construction of diversion dam on the Jarrahi river in order to required water suppling of irrigation and drainage network through of the main cannel locating in the left reverbank
The main and sub drainages construction in the length of 90 kilometer
The main and sub channel construction in the length of 78 kilometer
The technical structures of drainages and cannels construction in the number of 461 units
Flood control cannels construction in the length of 16 kilometer and the width 300 meter approximately and conducted to Shadeghan wetland